GIFSQ Tools · Module 18 — Manufacturing, Costing & Supply Chain · Tool 343 of 500
Work out the net raw material to buy for a production plan: gross requirement from the planned output, less the stock on hand, plus the safety stock you want to keep — the core of material requirements planning (MRP).
Try sample values — fills the form with the worked example below.
Method: Netting in material requirements planning (MRP): the gross requirement is the total material the plan consumes; stock on hand is netted off, and the safety stock is added back so the warehouse is not emptied. A negative net requirement means no purchase is needed.
Assumptions: the usage per unit is constant; stock on hand is usable stock (not quarantined or expired); lead time is not considered — use Tool 350 for the order timing.
Limitations: the tool plans one material at a time and does not split the order across suppliers or pack sizes; scrap and yield loss are not included — add them to the usage figure first.
Rounding: requirements to 2 decimal places; stock cover to 1 decimal place; intermediates unrounded.
This is a calculation aid, not a laboratory report — confirm against your accredited method before citing a value.
Enter values above to see results.
If the net requirement is 0, the plan is fully covered — check the expiry dates of the stock on hand before relying on it. Tool 343 of 500 — GIFSQ