TPM Quiz
GIFSQ ID: ART-2103
Test your knowledge with this free 20-question TPM quiz from Food Maintenance, Reliability & Asset Management, part…
What this quiz covers
TPM, total productive maintenance, is the idea that equipment care is everyone’s job, from operators to managers, and this quiz covers the system from its foundations to its measures. It starts with the core idea and the name: TPM stands for Total Productive Maintenance, total in the sense that everyone shares the responsibility for equipment care. When only maintenance owns it, the system never has enough eyes on the equipment. The foundation is 5S: sort, set in order, shine, standardize, sustain, the organized workplace that TPM builds on. You cannot maintain equipment properly in chaos, and sustain, the fifth S, means maintaining the standards through discipline and audits, not backsliding.
The quiz then covers the three pillars in practice. Autonomous maintenance puts routine care, cleaning, lubrication, inspection, and tightening, in operators’ hands, because the people closest to the equipment own its day to day condition. Cleaning is inspection, because hands on cleaning puts operators in close contact with the equipment, exactly where they notice leaks, cracks, and loose bolts before they become failures. Planned maintenance is scheduled, data driven specialist work that complements what operators do daily, replacing random firefighting with a plan built on evidence. Focused improvement is small kaizen teams systematically eliminating the six big losses: breakdowns, setup time, idling, reduced speed, defects, and startup losses. Early equipment management designs reliability and maintainability into new equipment from the start, because it is far cheaper than bolting maintainability onto a bad design later.
OEE is three numbers multiplied, not one
OEE, overall equipment effectiveness, multiplies availability, performance, and quality into one score, showing how much of the planned production time actually became good product at full speed. Availability measures uptime against planned production time, reflecting breakdown and setup losses. Performance compares actual speed against ideal speed, catching idling and slow running, including the small stops, brief idling and minor stops that never get logged as breakdowns but silently erode performance across every shift. Quality is good product divided by total product started, reflecting defects and rework. TPM success is measured by OEE trends, breakdown reduction, and cost per unit improving over time, not by meetings held or posters hung. Well cared equipment also supports food safety directly: it fails less, leaking less and shedding fewer foreign bodies into product.
How to use this quiz
Take the 20 questions in order, then read the answer explanations below the quiz. Each explanation names the correct answer and the reason behind it in plain words. If your plant runs TPM, or is thinking about it, note the two warnings in this quiz: TPM takes years of sustained effort to change culture and build capability, not a launch week, and it dies when treated as a maintenance department project without operator and management engagement.
Choose how you want to play
A short note: total productive maintenance in a food plant
TPM is Total Productive Maintenance: equipment care shared by everyone, operators to managers. It takes years of sustained effort to shift culture and build capability, and it fails when maintenance alone owns it, without operators and managers engaged.
OEE, Overall Equipment Effectiveness, is availability × performance × quality. Availability is uptime against planned production time, covering breakdown and setup losses. Performance compares actual speed with ideal speed, catching idling and slow running. Quality is good product over total product, covering defects and rework. Success is OEE trends rising, breakdowns falling and cost per unit dropping. The six big losses are breakdowns, setup, idling, reduced speed, defects and startup losses; small kaizen teams eliminate them one by one. Small stops are brief idling and minor stops that never count as breakdowns but erode performance.
Autonomous maintenance hands routine care to operators: cleaning, lubrication, inspection and tightening. Cleaning is inspection: hands-on cleaning puts operators where they notice leaks, cracks and looseness. Planned maintenance is specialist work on a data-driven schedule, backing up autonomous care. 5S is the organized workplace foundation: sort, set in order, shine, standardize, sustain; sustain means maintaining standards through discipline and audits. Early equipment management designs new equipment for reliability and maintainability from the outset. TPM needs training because new roles need new skills. Well-cared equipment breaks down less, so it leaks less and sheds fewer foreign bodies into product.
Care is everyone's job: the operator who cleans the machine is the first to spot the failure.
Questions and answers
Note: the player shuffles the questions and the answer options on every attempt, so the numbers in the player will not match the numbers in the questions and answers below. Match each answer by its wording.
Question 1: What is early equipment management in TPM?
Correct answer: Designing reliability and maintainability into new equipment from the start
Early equipment management starts before purchase: designing reliability and maintainability into new equipment from day one. It is far cheaper than bolting maintainability onto a bad design later.
Question 2: What does 'sustain' mean in 5S?
Correct answer: Maintaining the standards through discipline and audits, not backsliding
Sustain is the fifth S: maintaining the standards through discipline and audits so the gains do not erode. Without it, 5S slides back into the mess it cleaned up.
Question 3: What is OEE?
Correct answer: Overall Equipment Effectiveness: availability × performance × quality
OEE : Overall Equipment Effectiveness : multiplies availability, performance and quality into one score. It shows how much of the planned production time actually became good product at full speed.
Question 4: How does TPM support food safety?
Correct answer: Well-cared equipment fails less, leaking less and shedding fewer foreign bodies into product
Well-maintained equipment breaks down less often, so it leaks less oil and grease and sheds fewer foreign bodies into product. Equipment care is food safety at the equipment level.
Question 5: What is autonomous maintenance in TPM?
Correct answer: Operators performing routine care: cleaning, lubrication, inspection, and tightening
Autonomous maintenance puts routine care : cleaning, lubrication, inspection, tightening : in operators' hands. The people closest to the equipment own its day-to-day condition.
Question 6: Why does TPM emphasize training?
Correct answer: New roles (operator inspection, data use) need new skills
TPM gives operators new roles like inspection and data use that they did not have before. Those roles need new skills, so training is what makes the whole system actually work.
Question 7: How is TPM success measured?
Correct answer: OEE trends, breakdown reduction, and cost per unit improving over time
TPM success shows in OEE trends, falling breakdowns and lower cost per unit over time. Activity counts like meetings and posters measure effort, not results.
Question 8: What does the performance component of OEE measure?
Correct answer: Actual speed versus ideal speed, reflecting idling and slow running
The performance component compares actual operating speed against ideal speed. It catches the losses from idling and slow running that availability alone would miss.
Question 9: What is planned maintenance in TPM?
Correct answer: Scheduled, data-driven maintenance by specialists complementing autonomous care
Planned maintenance is scheduled, data-driven specialist work that complements what operators do daily. It replaces random firefighting with a maintenance plan built on evidence.
Question 10: What does TPM stand for?
Correct answer: Total Productive Maintenance
TPM stands for Total Productive Maintenance : total in the sense that everyone from operators to management shares the responsibility for equipment care.
Question 11: What does the quality component of OEE measure?
Correct answer: Good product versus total product, reflecting defects and rework
The quality component is good product divided by total product started. It reflects the losses from defects and rework that performance and availability would hide.
Question 12: Why is cleaning considered inspection in TPM?
Correct answer: Cleaning brings operators into close contact where they notice leaks, cracks, and looseness
Cleaning is inspection because hands-on cleaning puts operators in close contact with the equipment : exactly where they notice leaks, cracks and loose bolts before they become failures.
Question 13: What does the availability component of OEE measure?
Correct answer: Uptime versus planned production time, reflecting breakdown and setup losses
The availability component measures uptime against planned production time. It reflects the losses from breakdowns and setups that eat into scheduled production.
Question 14: What is the core idea of TPM?
Correct answer: Everyone from operators to managers shares responsibility for equipment care
The core idea of TPM is that equipment care is everyone's job, from operators to managers. When only maintenance owns it, the system never has enough eyes on the equipment.
Question 15: What is focused improvement (kaizen) in TPM?
Correct answer: Small teams systematically eliminating the six big losses
Focused improvement is small kaizen teams systematically hunting down the six big losses. It is structured elimination of waste, not decrees from above or a suggestion box nobody reads.
Question 16: How long does TPM implementation typically take?
Correct answer: Years of sustained effort to change culture and build capability
TPM is a culture change : new habits, new skills, new ways of working across the whole plant. That takes years of sustained effort, not a launch week.
Question 17: What is the role of 5S in TPM?
Correct answer: Sort, set in order, shine, standardize, sustain: the organized workplace foundation
5S : sort, set in order, shine, standardize, sustain : creates the organized workplace that TPM builds on. You cannot maintain equipment properly in chaos.
Question 18: What is the small-stop loss in TPM?
Correct answer: Brief idling and minor stops that don't count as breakdowns but erode performance
Small stops are the brief idling and minor stops that never get logged as breakdowns. Individually trivial, they silently erode performance across every shift.
Question 19: What is a common reason TPM implementations fail?
Correct answer: Treating it as a maintenance-department project without operator and management engagement
TPM dies when it is treated as a maintenance-department project. Without operator engagement and real management commitment, it never becomes the shared responsibility it needs to be.
Question 20: What are the six big losses TPM targets?
Correct answer: Breakdowns, setup time, idling, reduced speed, defects, and startup losses
The six big losses are breakdowns, setup and adjustment time, idling and minor stops, reduced speed, defects and rework, and startup losses. Focused improvement teams target them one by one.